bahrain al dur phase ii project puts the st20 main transformer into place
2021-7-7 16:41:59
on july 1, the st20 main transformer of bahrain al dur phase ii project
was put into place smoothly.
the main transformer is 11.3m long, 4.3m wide and 4.5m high, with
a transport weight of 206 tons. in order to ensure the smooth placement of the
main transformer, the project planned in advance and adopted the way of
hydraulic jack for track translation of the main transformer. at the same time,
the project group actively overcame the adverse effects of high temperature and
humidity weather and worked overtime to carry out the operation. during the
whole process, professionals kept a close eye on the site and coordinated
closely to ensure the smooth and accurate emplacement of the main transformer.
the smooth placement of st20 main transformer has laid a solid
foundation for the smooth development of subsequent installation work.